281 applications in the last 12 months within 5 km. Data aggregated from the local planning authority by planit.org.uk.
Last 30 days
4
Last 12 months
281
Pending
81
Approved
155
PendingApprovedRefusedWithdrawnOtherCentre of Hillam
- PendingThe installation of a 5m extension to existing lattice mast to accommodate 6 no. antenna, 1 no. 0.3m transmission dish and ancillary radio equipment, along with ancillary works thereto.Mast 59M From A L M Garage Services Moor Lane Trading Estate Sherburn In Elmet North Yorkshire LS25 6EPReceived 06 Nov 2026Telecoms26/07785/PNT564.35 km from centreNorth Yorkshire council
- PendingApplication to discharge Condition 40 (Gas Protection) for Zone B of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 02 Nov 2026Conditions23/00100/SUB394.68 km from centreWakefield council
- PendingNon-material amendment to application number 23/00100/REM04 Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone B for the erection of one B8 (Storage and Distribution Unit) (Unit 3A) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works to reduce the ride height of the building by 2 metres and changes to the external appearance of the building and layout of the developmentFormer Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Ferrybridge KnottingleyReceived 27 Oct 2026Amendment23/00100/NMC064.68 km from centreWakefield council
- PendingPermission in Principle for up to 2 No. dwellingsLand Adjacent To Number 22 Hillam Hall Lane Hillam North YorkshireReceived 20 Oct 2026Outline26/07210/PIP0.28 km from centreNorth Yorkshire council
- PendingApplication to discharge Condition 39 (Earthworks Verification) for Zone A of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley FerrybridgeReceived 06 Oct 2026Conditions23/00100/SUB384.68 km from centreWakefield council
- PendingDischarge of conditions 03 (materials), 04 (boundary treatments), 08 (surface water) and 09 (CMP) of approval ZG2025/1231/FUL Erection of a 3 bedroom cottage to land adjacent to (renewal of 2019/0176/FUL)7 St Marys Walk Hambleton North Yorkshire YO8 9GHReceived 04 Oct 2026Conditions26/06444/DISCON4.89 km from centreNorth Yorkshire council
- ApprovedNon-material amendment to application number 23/00100/REM02 Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone C for one B8 Storage and Distribution Unit (unit 2) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works to amend the external appearance of the building to allow for heating and ventilation ductwork to be installed on the building and a change from a solid metal door into a glazed door.Former Coal Yard, Ferrybridge 'C' Power Station, Kirkhaw Lane, Ferrybridge, KnottingleyReceived 04 Oct 2026Decided 27 Oct 2026Amendment23/00100/NMC054.68 km from centreWakefield council
- PendingApproval of details required under condition 9 (Soil Resource Management Plan) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Selby Road Monk Fryston North Yorkshire LS25 5LEReceived 30 Sept 2026Conditions26/06360/DISCON3.81 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 10 (Arboricultural Method Statement) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North YorkshireReceived 29 Sept 2026Conditions26/06316/DISCON3.81 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 41 (Renewable, Low Carbon or Decentralised Energy Source) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North YorkshireReceived 29 Sept 2026Conditions26/06317/DISCON3.81 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 35 (Surface Water Drainage Scheme) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Selby Road Monk Fryston North Yorkshire LS25 5LEReceived 29 Sept 2026Conditions26/06318/DISCON3.81 km from centreNorth Yorkshire council
- PendingApproval of details required under conditions 36 (Investigation and Risk Assessment) and 37 (Remediation Scheme) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North YorkshireReceived 29 Sept 2026Conditions26/06319/DISCON3.81 km from centreNorth Yorkshire council
- PendingErection of single storey rear extension35 Fairfield Fairburn North Yorkshire WF11 9LBReceived 27 Sept 2026Full26/06256/FUL3.4 km from centreNorth Yorkshire council
- PendingChange of use of existing agricultural barn together with associated garden and parking area, sewage system and associated works.Bumble Barn Green Lane Monk Fryston North Yorkshire LS25 5EJReceived 24 Sept 2026Full26/06174/FUL1.32 km from centreNorth Yorkshire council
- PendingT1 - sycamore - removal of the 1 lowest main limb on the house side cut to the fed line in the attached picture and draw back the remaining upper crown by 2.5m on the house side.Wells Cottage High Street South Milford North Yorkshire LS25 5AQReceived 24 Sept 2026Trees26/06214/TPO3.17 km from centreNorth Yorkshire council
- PendingT19 - Polar 20M high - Reduce canopy all round to its previous pollard points. This will prevent the tree from outgrowing its situation and prolong its life in the space it has.6 The Limes South Milford North Yorkshire LS25 5NHReceived 23 Sept 2026Trees26/06142/TPO2.9 km from centreNorth Yorkshire council
- PendingT1 3x lime trees - To remove any deadwood within the canopy. T2 ash tree - for removal due to signs of ash die back2 The Limes South Milford North Yorkshire LS25 5NHReceived 23 Sept 2026Trees26/06158/TPO2.92 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 11 (Landscaping Details) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South MilfordReceived 21 Sept 2026Conditions26/06046/DISCON3.81 km from centreNorth Yorkshire council
- ApprovedNon-material amendment to application number 23/00100/REM01 Approval of Reserved Matters pursuant to 23/00100/S7301 (Access, Appearance, Landscaping, Layout and Scale) at Development Zone A for development of a data centre campus with associated energy and electrical infrastructure, visitor reception buildings, security gatehouses and ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works, to amend the wording of the approved plans condition (Condition 2) by making alterations to the layout and design of the substation.Land At Former Coal Yard, Ferrybridge Kirkhaw Lane Ferrybridge Wakefield WF11 8RDReceived 21 Sept 2026Decided 12 Oct 2026Amendment23/00100/NMC044.68 km from centreWakefield council
- PendingListed building consent for the replacement of failed windows to southern elevation and damaged gutteringBirkin House Haddlesey Road Birkin North Yorkshire WF11 9LTReceived 20 Sept 2026Heritage26/05975/LB3.04 km from centreNorth Yorkshire council
- PendingTwo storey side and single storey rear extensions40A Sutton Lane Byram North Yorkshire WF11 9DPReceived 16 Sept 2026Full26/05911/FUL4.11 km from centreNorth Yorkshire council
- PendingApplication to re-discharge Condition 23 (Drainage) of Planning Permission 23/00100/S7301 For Zone C and The Estate RoadFormer Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 16 Sept 2026Conditions23/00100/SUB374.68 km from centreWakefield council
- RefusedConversion of existing barn to form 3 No. dwellingsThe Stables Old Vicarage Lane Monk Fryston North Yorkshire LS25 5EAReceived 15 Sept 2026Decided 21 Oct 202626/05883/PBR0.62 km from centreNorth Yorkshire council
- PendingDischarge of conditions 12 (BCEMP) and 13 (EMP) of approval 2019/0547/EIA Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North Yorkshire LS25 5LEReceived 15 Sept 2026Conditions26/05884/DISCON3.81 km from centreNorth Yorkshire council
- Approved with conditionsDischarge of condition 07 (surface water) of approval SELZG2023/1051/FUL Partial demolition, conversion and extension of existing livery buildings to form a residential dwellingGranary Farm Pighill Nook Road Hillam North Yorkshire LS25 5HXReceived 15 Sept 2026Decided 21 Oct 2026Conditions26/05898/DISCON1.73 km from centreNorth Yorkshire council
- PendingDischarge of conditions 3 (CEMP), 4 (BNG Plan) and 5 (Habitat Management and Monitoring Plan) from approved application 24/01465/FUL.Former Ferrybridge Substation Stranglands Lane Ferrybridge WF11 8DXReceived 15 Sept 2026Conditions24/01465/SUB014.63 km from centreWakefield council
- PendingDischarge of conditions 07 (details) and 08 (refuse) of approval 2019/0547/EIA Proposed construction of a motorway service areaLand At Lumby Selby Road Lumby South Milford North Yorkshire LS25 5LEReceived 14 Sept 2026Conditions26/05847/DISCON3.81 km from centreNorth Yorkshire council
- Approved with conditionsApproval of details required under condition 4 (Amenity Building Details) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North YorkshireReceived 14 Sept 2026Decided 11 Nov 2026Conditions26/05848/DISCON3.81 km from centreNorth Yorkshire council
- PendingErection of single storey rear extension8 Westfield Close South Milford North Yorkshire LS25 5ANReceived 10 Sept 2026Full26/05854/FUL3.13 km from centreNorth Yorkshire council
- PendingVariation of condition 2 (approved plans) for changes to the size of extension of planning permission SELZG2025/0025/HPA - Erection of single storey rear/side extension5 Water Lane Monk Fryston North Yorkshire LS25 5DZReceived 09 Sept 2026Conditions26/05686/DVCON0.81 km from centreNorth Yorkshire council
- PendingApplication to discharge Condition 41 (Gas Protection) for Unit 1 (Zone C) of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 08 Sept 2026Conditions23/00100/SUB364.68 km from centreWakefield council
- PendingApproval of details required under conditions 5 (Engineering Drawings), 9 (Highway Mitigation), 12 (Travel Plan) and 15 (Noise Mitigation), 18 (Ground Gas Risk Assessment) of Planning Permission SEL2022/1236/FULM (APP/U2750/W/25/3367176) - Residential development consisting of 66 dwellings, with associated landscaping and highways, demolition and off-site highways worksVacant Green Field Land And Areas Related To Previous Plant Nursery Garden Lane Sherburn In ElmetReceived 03 Sept 2026Conditions26/05521/DISCON4.71 km from centreNorth Yorkshire council
- ApprovedCertificate of lawfulness for erection of single storey rear extension and single storey front entrance porchThe Poplars 177 Moor Lane Sherburn In Elmet North Yorkshire LS25 6DXReceived 02 Sept 2026Decided 21 Oct 2026Outline26/05470/CLOPUD4.87 km from centreNorth Yorkshire council
- PendingVariation of conditions 2 (approved plans), 3 (materials) and 4 (landscaping scheme) for changes to materials and layout of planning permission SEL2023/0366/FUL (SELAP/2024/0036/REF) - Erection of detached dwelling and garage following demolition of existing buildingMulberry Farm Butts Lane Lumby North Yorkshire LS25 5JAReceived 01 Sept 2026Conditions26/05453/DVCON2.71 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 27 (Construction Environmental Management Plan) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South MilfordReceived 31 Aug 2026Conditions26/05435/DISCON3.81 km from centreNorth Yorkshire council
- PendingApproval of details required under condition 40 (Training and Employment Management Plan) of Planning Permission SEL2019/0547/EIA - Proposed construction of a motorway service areaLand At Lumby Lumby South MilfordReceived 31 Aug 2026Conditions26/05436/DISCON3.81 km from centreNorth Yorkshire council
- PendingReplacement of existing building with stables and construction of access trackLand South Of West Ings Lane KnottingleyReceived 27 Aug 2026Full26/01568/FUL4.63 km from centreWakefield council
- RefusedPrior notification for the change of use of agricultural buildings to 5 No dwellings (Use Class C3) and associated operational developmentBurton Common Farm Burton Common Lane Burton Salmon North Yorkshire LS25 5NBReceived 23 Aug 2026Decided 07 Oct 202626/05229/PBR1.29 km from centreNorth Yorkshire council
- ApprovedPrior notification for demolition of plant hire building & associated dwellinghouseCrossroads Hire Centre Selby Road Monk Fryston North Yorkshire LS25 5JEReceived 18 Aug 2026Decided 23 Sept 2026Outline26/05071/PND1.63 km from centreNorth Yorkshire council
- ApprovedApplication for consent to fell 1No Acer Flamingo tree (T3) and removal of lower branches of 1No Silver Birch tree (T2) below 3m on neighbouring property and removal of the extremities of branches up to a height of 2m on applicants property.The Brambles Main Street Hillam North Yorkshire LS25 5HHReceived 17 Aug 2026Decided 27 Sept 2026Trees26/05083/TCON0.07 km from centreNorth Yorkshire council
- PendingErection of single storey rear extension with garage conversion45 Eversley Court Sherburn In Elmet North Yorkshire LS25 6BPReceived 16 Aug 2026Full26/05028/FUL4.62 km from centreNorth Yorkshire council
- ApprovedDemolition of existing conservatory and construction of new utility room, raise existing garage roof to create storage space, removal of existing 4750mm high Leylandii hedging and erection of 3000mm high evergreen living fence to site boundaryRedmyer 3 Briardene Court Moor Lane Sherburn In Elmet North Yorkshire LS25 6PGReceived 13 Aug 2026Decided 04 Oct 2026Full26/04918/FUL4.99 km from centreNorth Yorkshire council
- PendingSection 73 application to vary conditions 15 (highways) and 20 (highways) of approval 2019/0547/EIA Proposed construction of a motorway service areaLand At Lumby Lumby South Milford North YorkshireReceived 12 Aug 2026Conditions26/04892/DVCMAJ3.81 km from centreNorth Yorkshire council
- PendingDischarge of condition 19 (Construction Management Plan) of approval 2019/0547/EIA Proposed construction of a motorway service areaLand At Lumby Lumby South MilfordReceived 12 Aug 2026Conditions26/04899/DISCON3.81 km from centreNorth Yorkshire council
- Approved with conditionsDischarge of conditions 05 (bridging or culverting of watercourse) , 08 (Construction Management Plan), 10 (surface water), 14 (root protection area) and 17 of approval ZG2025/1144/FUL Erection of a self-build replacement dwelling with new accessTalania Hillam Common Lane Hillam North Yorkshire LS25 5HUReceived 11 Aug 2026Decided 13 Oct 2026Conditions26/04864/DISCON0.55 km from centreNorth Yorkshire council
- ApprovedGantry/Totem SignageFerrybridge Mfe Limited Kirkhaw Lane Knottingley WF11 8RDReceived 11 Aug 2026Decided 05 Oct 2026Advertising26/01448/ADV4.56 km from centreWakefield council
- RefusedDemolition of the existing barn, and erection of a replacement building to accommodate two indoor padel courts, together with associated parking and landscapingPollums House Farm Mile Gap To Pollums Farm Monk Fryston North Yorkshire LS25 5LDReceived 09 Aug 2026Decided 04 Oct 2026Full26/04774/FUL2.97 km from centreNorth Yorkshire council
- PendingChange of use for an existing residential outbuilding and sauna to be used as a wellness center including the provision of a new toilet block and shower/changing facilityWestholme Farm Common Lane South Milford North Yorkshire LS25 5BXReceived 09 Aug 2026Full26/04778/FUL2.61 km from centreNorth Yorkshire council
- PendingErection of new dwelling with access off Old Vicarage Lane4 Old Vicarage Court Monk Fryston North Yorkshire LS25 5FWReceived 09 Aug 2026Full26/04780/FUL0.79 km from centreNorth Yorkshire council
- PendingSection 73 application to vary conditions 02 (plans) and 14 (highways) of approval ZG2025/0107/S73 Section 73 application to vary conditions 02 (plans) and 14 (highways) of approval 2021/1402/S73 Section 73 application to vary conditions 02 (approved plans), 14 (vehicle access, parking, manoeuvring and turning areas) and 22 (refuse derived fuel fired combined heat and power plant) of approval 2020/0355/S73 Section 73 application to vary/remove condition 02 (approved plans) of planning permission reference 2018/0898/EIA Section 73 application to vary condition 02 of approval 2016/1456/EIA Proposed Installation of a Refused Derived Fuel (RDF) fired Combined Heat and Power (CHP) plant with 8000m2 Factory Extension and Associated Infrastructure granted on 03 April 2019 granted on 12 February 2021Kingspan Insulation Ltd Enterprise Way Sherburn In Elmet North Yorkshire LS25 6NAReceived 05 Aug 2026Conditions26/04654/DVCMAJ4.6 km from centreNorth Yorkshire council
- PendingRestoration and aftercare programmeBrotherton Quarry, Byram Park, KnottingleyReceived 05 Aug 2026NY/2026/0216/AFT2.72 km from centreNorth Yorkshire council
- ApprovedInstallation of a gabions to an existing watercourse (retrospective)Spring Cottage Ingthorns Road South Milford North Yorkshire LS25 5PPReceived 04 Aug 2026Decided 18 Oct 2026Full26/04609/FUL1.81 km from centreNorth Yorkshire council
- PendingApplication to discharge Condition 27 (Artificial Lighting) for the estate road of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane . KnottingleyReceived 03 Aug 2026Conditions23/00100/SUB354.68 km from centreWakefield council
- ApprovedInstallation of cladding and new railings to the existing rail bridge with associated engineering worksRail Bridge Above Kirkhaw Lane Ferrybridge WakefieldReceived 02 Aug 2026Decided 30 Oct 2026Full26/01370/FUL4.59 km from centreWakefield council
- PendingDemolition of existing garage and erection of two storey side extension with rear facing dormer window and a new detached garage1 Cardinal Close Sherburn In Elmet North Yorkshire LS25 6DWReceived 29 Jul 2026Full26/04469/FUL4.93 km from centreNorth Yorkshire council
- ApprovedLawful development certificate for use of the building as a storage building with ancillary private hobby workshop use within part of the building.The Barn Butts Lane Lumby North Yorkshire LS25 5JAReceived 28 Jul 2026Decided 21 Sept 2026Amendment26/04419/CLEUD2.82 km from centreNorth Yorkshire council
- ApprovedGarage conversion with side extension and porch to front19 Appletree Drive Hambleton North Yorkshire YO8 9QGReceived 28 Jul 2026Decided 19 Oct 2026Full26/04451/FUL4.38 km from centreNorth Yorkshire council
- ApprovedInstallation of roof dormer, demolition of existing detached double garage and construction detached single garage17 Wolsey Croft Sherburn In Elmet North Yorkshire LS25 6DRReceived 27 Jul 2026Decided 29 Oct 2026Full26/04402/FUL4.88 km from centreNorth Yorkshire council
- Approved with conditionsApplication to Discharge Condition 39 (Earthworks Verification) of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Ferrybridge Knottingley WF11 8RDReceived 27 Jul 2026Decided 09 Sept 2026Conditions23/00100/SUB334.68 km from centreWakefield council
- RefusedLawful development certificate for proposed single storey extension to the back of the garage joining up to the existing kitchen to create a wet room and large kitchen area4 Rose Lea Close Hillam North Yorkshire LS25 5HJReceived 22 Jul 2026Decided 06 Oct 2026Outline26/04225/CLOPUD0.12 km from centreNorth Yorkshire council
- ApprovedErection of a bat mitigation barnLand Off Hagg Lane Sherburn-in-Elmet North YorkshireReceived 21 Jul 2026Decided 07 Oct 2026Full26/04177/FUL4.03 km from centreNorth Yorkshire council
- ApprovedNon material amendment to application number 23/00100/REM04 Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone B for the erection of one B8 (Storage and Distribution Unit) (Unit 3A) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works, to amend the wording of approved plans condition (Condition 2 Approved Plans).Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley FerrybridgeReceived 21 Jul 2026Decided 17 Aug 2026Amendment23/00100/NMC034.68 km from centreWakefield council
- UnresolvedT1 - Sycamore - Remove deadwood from the canopy limiting the wound and size to a maximum dimension of 50mm. T2 - Sycamore - Lateral reduction on the west side of the lower canopy side by 1.5 - 2m or to the nearest growth point and limited the wound size to 75mm. Reduce elongated limb growing towards property by 1 to 1.5m or to the nearest growth point and limit the wound size to 75mm. T3 - Sycamore - Reduce limb growing towards property by 1.5 to 2m or to the nearest growth point and limited the wound size to 75mm.55A Hill Top Knottingley WF11 9AQReceived 19 Jul 2026Decided 14 Sept 2026Trees26/01288/TPO4.97 km from centreWakefield council
- RefusedCrown Reduce G1 and T1 in height and overhang by 2 to 3 meters.55 Hill Top Knottingley WF11 9AQReceived 19 Jul 2026Decided 14 Sept 2026Trees26/01297/TPO4.97 km from centreWakefield council
- PendingApplication to Discharge Condition 23 (Drainage) for Zone B of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 13 Jul 2026Conditions23/00100/SUB314.68 km from centreWakefield council
- Approved with conditionsApplication to Discharge Condition 30 (Energy) for Units 1 & 2 of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 13 Jul 2026Decided 09 Sept 2026Conditions23/00100/SUB324.68 km from centreWakefield council
- WithdrawnFront alterations including extension at 1st floor, alterations to the roof line to form a gable, alterations to glazing at ground and first floor, minor demolition at ground floor to create a covered entrance areaStone House Old Quarry Lane Lumby North Yorkshire LS25 5JAReceived 09 Jul 2026Decided 24 Sept 2026Full26/03878/FUL2.55 km from centreNorth Yorkshire council
- ApprovedFirst floor side extension above garageMulberry House High Street Brotherton North Yorkshire WF11 9EYReceived 08 Jul 2026Decided 26 Aug 2026Full26/03836/FUL3.95 km from centreNorth Yorkshire council
- Approved with conditionsApplication to Discharge 11 (Construction Environmental Management Plan (CEMP), Condition 12 (Construction Traffic Management Plan (CTMP) and Condition 21 (Temporary Drainage) for Stage 5 of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 08 Jul 2026Decided 21 Oct 2026Conditions23/00100/SUB304.68 km from centreWakefield council
- PendingRear First Floor BalconyThe Orchards 52A Sutton Lane Byram North Yorkshire WF11 9DPReceived 07 Jul 2026Full26/03805/FUL4.16 km from centreNorth Yorkshire council
- RefusedReduce height by 30% to 1 No Sycamore Tree (T9) protected by TPO No 7/19955 The Willows Hambleton North Yorkshire YO8 9GUReceived 07 Jul 2026Decided 15 Sept 2026Trees26/03814/TPO4.44 km from centreNorth Yorkshire council
- RefusedErection of first floor side extension to form a bedroom with en-suite and dressing areaVictoria House Roe Lane Birkin North Yorkshire WF11 9LRReceived 06 Jul 2026Decided 27 Aug 2026Full26/03768/FUL2.91 km from centreNorth Yorkshire council
- PendingApplication to Discharge Condition 19 (Landscape and Ecological Management Plan (LEMP)) for development Zone B of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 06 Jul 2026Conditions23/00100/SUB284.68 km from centreWakefield council
- PendingApplication to Discharge Condition 11(Construction Environmental Management Plan (CEMP)); Condition 12 (Construction Traffic Management Plan (CTMP)); Condition 21 (temporary surface water drainage); Condition 23 (foul and surface water drainage); Condition 29 (works adjacent A1(M)); Condition 38 (remediation strategy and verification plan); and Condition 40 (gas protection measures) for development Zone A of Planning Permission 23/00100/S7301Former Coal Yard Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge WF11 8RDReceived 06 Jul 2026Conditions23/00100/SUB294.68 km from centreWakefield council
- ApprovedInternally Illuminated Signage SchemeFormer Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 06 Jul 2026Decided 20 Aug 2026Advertising26/01211/ADV4.55 km from centreWakefield council
- PendingLoft Conversion with rear dormer extension, two storey front extension and associated alterations25A Wolsey Croft Sherburn In Elmet North Yorkshire LS25 6DRReceived 05 Jul 2026Full26/03715/FUL4.87 km from centreNorth Yorkshire council
- PendingErection of new dwelling after partial demolition of existing garagesGarages At The Mews Butts Lane Lumby North Yorkshire LS25 5BJReceived 02 Jul 2026Full26/03682/FUL2.59 km from centreNorth Yorkshire council
- Approved with conditionsApplication to Discharge Condition 27 (Artificial Lighting) for Units 1 and 2 (within Zone C) of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 30 Jun 2026Decided 28 Jul 2026Conditions23/00100/SUB274.68 km from centreWakefield council
- RefusedNon material amendment of approval 2006/0727/FUL Proposed erection of 8 No. 5 and 4 bedroomed dwellings with garages and 6 No. 2 bedroomed apartments on land to the rear27 Lunnsfield Lane Fairburn North Yorkshire WF11 9LEReceived 28 Jun 2026Decided 23 Jul 2026Amendment26/03516/AMENDS3.51 km from centreNorth Yorkshire council
- PendingRear two storey extension2 Prebendal Close Monk Fryston North Yorkshire LS25 5ESReceived 28 Jun 2026Full26/03548/FUL0.87 km from centreNorth Yorkshire council
- Approved with conditionsApplication to Discharge Condition 18 (Biodiversity Retention and Enhancement Scheme (BRES) and Condition 19 (Landscape and Ecological Management Plan (LEMP) for development Zone A of Planning Permission 23/00100/S7301Former Coal Yard Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge WF11 8RDReceived 28 Jun 2026Decided 22 Sept 2026Conditions23/00100/SUB264.68 km from centreWakefield council
- PendingChange of use of land from agricultural use to private, non-commercial equestrian use (Sui Generis), together with the retrospective retention of a mobile double stable block (retrospective)Akenfall Cottage Hillam Lane Hillam North Yorkshire LS25 5HWReceived 25 Jun 2026Full26/03484/FUL0.49 km from centreNorth Yorkshire council
- Approved with conditionsApplication to discharge Condition 41 (Gas Protection) for Unit 2 (Zone C) of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 25 Jun 2026Decided 07 Sept 2026Conditions23/00100/SUB254.68 km from centreWakefield council
- ApprovedApplication for consent to fell and stump removal to 1No Lime tree covered by TPO 8/1979Parkview Chapel Street Hillam North Yorkshire LS25 5HPReceived 23 Jun 2026Decided 16 Sept 2026Trees26/03378/TPO0.35 km from centreNorth Yorkshire council
- PendingTwo storey side extension3 Westfield Close South Milford North Yorkshire LS25 5ANReceived 23 Jun 2026Full26/03388/FUL3.12 km from centreNorth Yorkshire council
- Approved with conditionsApplication to discharge Condition 44 (Employment and Skills Plan) for Unit 2 (Zone c) of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 22 Jun 2026Decided 28 Jul 2026Conditions23/00100/SUB244.68 km from centreWakefield council
- PendingRemoval of 4 No. dilapidated garages and the erection of 1 No. new double garage and adjoining timber car port (retrospective)2 School View Monk Fryston North Yorkshire LS25 5EEReceived 16 Jun 2026Full26/03178/FUL0.71 km from centreNorth Yorkshire council
- PendingErection of new garage block, car port and ancillary accommodation over11 Milford Road South Milford North Yorkshire LS25 5ADReceived 14 Jun 2026Full26/03097/FUL3.2 km from centreNorth Yorkshire council
- Approved with conditionsApplication to Discharge Condition 43 (Acoustic Fencing) as amended under 23/00100/NMC02 of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 14 Jun 2026Decided 28 Jul 2026Conditions23/00100/SUB234.68 km from centreWakefield council
- ApprovedApplication for consent to fell 1No Sycamore tree to ground level and remove stump by stump grinding in the conservation areaRoselea Chapel Street Hillam North Yorkshire LS25 5HPReceived 11 Jun 2026Decided 20 Jul 2026Trees26/03080/TCON0.11 km from centreNorth Yorkshire council
- ApprovedApplication for consent for a 2-metre lateral reduction, crown lift to give a 4-metre ground clearance, and removal of epicormic growth to 1No Horse Chestnut tree covered by TPO 7/1995.2 The Willows Hambleton North Yorkshire YO8 9GUReceived 09 Jun 2026Decided 13 Oct 2026Trees26/02950/TPO4.4 km from centreNorth Yorkshire council
- PendingErection of a livestock buildingLow Farm Bond Ings Sherburn In Elmet North Yorkshire LS25 6FWReceived 09 Jun 2026Full26/02964/FULMAJ3.3 km from centreNorth Yorkshire council
- PendingModular building to extend existing mixed use cricket pavilion and nursery settingHillam And Monk Fryston Cricket Club Chapel Street Hillam West Yorkshire LS25 5HPReceived 28 May 2026FullSELZG2026/0499/FUL0.51 km from centreNorth Yorkshire council
- PendingModular building to extend existing mixed use cricket pavilion and nursery settingHillam And Monk Fryston Cricket Club Chapel Street Hillam West Yorkshire LS25 5HPReceived 28 May 2026FullSELZG2026/0499/FUL0.51 km from centreSelby council
- PendingModular building to extend existing nursery settingHillam And Monk Fryston Cricket Club Chapel Street Hillam West Yorkshire LS25 5HPReceived 28 May 2026FullZG2026/0499/FUL0.51 km from centreSelby council
- Approved with conditionsApplication to Discharge Condition 28 (Security and Crime) and Condition 31 (Waste Management Strategy) for Unit 2 within development Zone C of Planning Permission 23/00100/S7301Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane KnottingleyReceived 27 May 2026Decided 17 Sept 2026Conditions23/00100/SUB224.68 km from centreWakefield council
- ApprovedReconstruction of existing conservatory in oak framed structure with raised apex, new eye brow dormer to front facing roof slope and new oak framed entrance porchDarnley Home Farm Hillam Common Lane Hillam Leeds West Yorkshire LS25 5HRReceived 25 May 2026Decided 02 Aug 2026FullSELZG2026/0487/HPA1.86 km from centreNorth Yorkshire council
- ApprovedReconstruction of existing conservatory in oak framed structure with raised apex, new eyebrow dormer to front facing roof slope and new oak framed entrance porchDarnley Home Farm Hillam Common Lane Hillam Leeds West Yorkshire LS25 5HRReceived 25 May 2026Decided 02 Aug 2026FullSELZG2026/0487/HPA1.86 km from centreSelby council
- ApprovedReconstruction of existing conservatory in oak framed structure with raised apex, new eyebrow dormer to front facing roof slope and new oak framed entrance porchDarnley Home Farm Hillam Common Lane Hillam Leeds West Yorkshire LS25 5HRReceived 25 May 2026Decided 02 Aug 2026FullZG2026/0487/HPA1.86 km from centreSelby council
- ApprovedSection 73 application to remove condition 11 (landscaping) of approval 2021/0372/FULM Temporary change of use of part of former colliery to fall within use classes E(g)(i), B2 and B8, the erection of modular office, welfare and storage buildings for a temporary period of 5 years and associated operations to provide car parking facilitiesSherburn Rail Freight Terminal Lennerton Lane Sherburn In Elmet Leeds North Yorkshire LS25 6JEReceived 21 May 2026Decided 15 Sept 2026ConditionsSELZG2026/0480/S733.81 km from centreNorth Yorkshire council
Showing the 100 most recent of 281 within 5 km. Planning data from PlanIt, updated nightly. For older or narrowly defined applications, consult the council portal directly.